Skip to main content

Waterway Blvd Multi-use Path Elevation

The Waterway Boulevard Multi-Use Path Elevation Project is a strategic infrastructure investment that enhances both mobility and flood protection along a critical corridor on Isle of Palms. Designed to function as a dual-purpose asset, the elevated path not only improves safety and accessibility for pedestrians and cyclists, but also serves as a flood barrier that helps reduce the impacts of tidal flooding on surrounding areas. 

By raising the pathway to a more resilient elevation, the project supports reliable, year-round use while contributing to the City’s broader efforts to mitigate flooding and strengthen coastal resilience.

Updates

August 10, 2026 – The crew should be finishing up drainage around 32nd Avenue while the utility contractor finishes utility offsets at Sparrow Drive and 3605 Waterway Blvd in the next week or so. As the utility offsets are completed, the drainage contractor will work on finishing the drainage and pathway in the same areas. We’re still waiting on AT&T to relocate their utilities around 32nd Avenue...
August 3, 2026 – While attempting to install the C8 structure on Saturday (08/01), The Bastion Group encountered groundwater issues. As a safety precaution, they have extended the 32nd Avenue closure and barricades while the excavation remains open. They will have additional pumps onsite Monday (08/03) to control the groundwater and complete the structure installation.
Paved path
July 14, 2026 – Significant progress has been made. Pathway paving is complete from 21st to 29th Avenues. Demolition of the original path is complete from 29th Ave to Timber Ln, and the original path remains from Timber Ln to 41st Ave. Good news for walkers and cyclists: The majority of the pathway will remain open throughout the paving process. The compacted gravel will serve as a temporary...
A digger digging up the existing asphalt sidewalk
April 23, 2026 - Pathway construction is underway. The contractor is working from 21st to 30th Avenue this week, currently demolishing the existing sidewalk at 21st & Waterway. The pathway will remain open for walking and biking during the paving process — a compacted gravel surface will be in place initially until final paving is complete.
Waterway Blvd construction
April 7, 2026 – New drainage has been installed at 22nd Avenue, and a swale has been graded in front of 2200 & 2202 Waterway Blvd to improve water flow through the new drainage system. The City has also been coordinating a cleaning of the outfall pipes as part of this work. The contractor has moved to 23rd Avenue and is awaiting permits to cut the road. Over the next couple of weeks, work will...