Skip to main content

City-Managed Beach Restoration Projects

2026 Offshore Renourishment Project

The city is planning a beach renourishment project as part of the City’s long-term Comprehensive Beach Management Plan. Up to 2.5 million cubic yards of material will be placed along 19,200 linear feet of beach (1.7M in Wild Dunes and 800K on the southern end of the Island.) 

The nourishment will be separated into three separate reaches and involves construction of a dune and a berm.

The material will be dredged from an offshore borrow site located around ~2 miles southeast of the Island Pier.

Alternatives Analysis

The Isle of Palms City Council has voted to hire Foth/Olsen to conduct a study of the City’s beach restoration strategy.

Bringing in a new contractor could introduce fresh and innovative approaches aimed at extending the longevity of future sand placements, reducing the frequency of large scale restorations.

Any recommended alternatives would need to be implemented within a few years of the 2026 restoration project to help maximize the lifespan of the newly placed sand.

Tentative Construction Schedule
Pre-Construction Meeting30 June
Contractor mobilizationJuly
Anticipated first day pumping in Reach 117 July
Reach 1 nourishment duration50 days
Anticipated first day pumping in Reach 29 September
Reach 2 nourishment duration45 days
Anticipated first day pumping in Reach 31 Nov
Reach 3 nourishment duration45 days
DemobilizationDecember

Where will construction occur?

View this map in full screen ➜

 

Frequently Asked Questions (FAQs)

Will the beach be closed?

No. Beach renourishment work will take place in sections of approximately 300 yards at a time.

In most cases, pedestrians will be able to walk around the fenced work area. The only exception may be during temporary dune construction activities, when access around a work zone could be briefly restricted.

Beachgoers will also be able to safely cross the dredge pipeline using sand ramps to access the ocean.

Will the project be loud or disturbing at night?

This project will require heavy machinery operating around the clock. Residents may notice some light and backup alert sounds during nighttime hours. Work is expected to progress at a rate of 100–300 feet per day, so any disturbances in your area should pass within a night or two.

 

What will construction look like?

 

How is this project funded?

The City has received $1.5 million of the total $5.3 million requested in state funding for the major beach renourishment project. An estimated $27 million will come from local sources, including funds raised by the Wild Dunes Community Association, to complete the work. The amounts of each contribution are still to be determined.

All other City beach restoration efforts are being funded through a combination of the City's Beach Preservation Fund, Wild Dunes Community Association (WDCA) contributions, and state and federal sources.

View Coastal Science and Engineering's presentation of June 2026 to City Council ➜

Updates

June 26, 2026 – Coastal Science and Engineering (CSE) has provided us with the latest estimates on a construction schedule available on our beach page. Will the beach be closed? No. Beach renourishment work will take place in sections of approximately 300 yards at a time. In most cases, pedestrians will be able to walk around the fenced work area. The only exception may be during temporary dune...
June 8, 2026 - The South Carolina Department of Environmental Services has approved the City of Isle of Palms' request for dredging and beach renourishment along the island's shoreline. The permit is valid for five years. Contractor Marinex is expected to begin setting up equipment and staging areas in late June, with sand pumping expected to get underway shortly after the Fourth of July...
May 26, 2026 - The SC Department of Environmental Services has approved the City's request for dredging and beach renourishment along the Isle of Palms shoreline. This permit is valid for five years Beach Renourishment Major Permit
May 14, 2026 – In a special session of City Council on May 12, the City awarded the full 2026 beach renourishment project to Marinex. Marinex will start on the northern end of the Island, and work their way South. A map of the construction areas are available on our website. We should start to see mobilization late May to early June, and expect to see the first sand placement mid to late June. If...
April 2, 2026 - Beachfront property owners who abut a section of the beach that is scheduled to undergo a renourishment starting in the summer of 2026 were invited to meet with City staff, attorneys, and coastal consultants to learn about the 2026 Beach Renourishment Project, and specifically, the easements that the City is working to secure. Most of the 2026 renourishment project will take place...
March 24, 2026 - The City of Isle of Palms has received and opened bids for the 2026 Renourishment Project. A winner is expected to be announced on April 28 in the City Council meeting. Bidder 1 Bidder 2 Bidder 3 Bidder 4 Bidder 5 Weeks Marine Inc Callan Marine LTD Marinex Construction Norfolk Dredging Great Lakes Dredge and Dock Co Bid Item A1 Mobilization - Base Bid $9,750,000.00 $11,245,000.00...
02/27/2026 - The City of Isle of Palms has been awarded a $1.5 million grant from the South Carolina Department of Parks, Recreation & Tourism to support beach renourishment efforts, helping offset costs for the City’s 2026 beach renourishment project. Pursuing additional state and federal funding is a key priority identified in the City’s 13 January 2026 Strategic Planning session. This award is...
The City of Isle of Palms has officially issued Requests for Bids (RFBs) for the 2026 Beach Renourishment Project. This project is part of the City’s ongoing commitment to preserving Isle of Palms’ shoreline, protecting public and private property, and maintaining a healthy beach for residents and visitors. Beach renourishment helps restore sand lost through natural erosion and storm events...
02/06/2026 - The permits requested for the large off-shore renourishment project were finalized and submitted in September. Next steps include developing a financial share agreement with Wild Dunes Community Association which is being discussed by the Public Facilities Committee. Soliciting bids are planned for this month (February)
12/9/2025 - You may notice some encouraging changes along our shoreline. The images below show the early stages of a sand shoal moving onshore and naturally adding sand to the section of the Isle of Palms beach near Beachwood East and Dunecrest Ln. When you compare the “X” marked on each image, you can clearly see the shoreline beginning to build outward. While this is a positive development, it’s...
beach restoration 11.5.25
The City continues to make steady progress in restoring its beaches and addressing ongoing erosion concerns. Read on for the latest project updates. Public Input & Permit Application The public comment period for the nourishment permit application is currently open. Interested stakeholders can view the public notice and how to submit comments to the state via Public Notices or the U.S. Army Corps...