Skip to main content

City-Managed Beach Restoration Projects

2026 Offshore Renourishment Project

The city is planning a beach renourishment project as part of the City’s long-term Comprehensive Beach Management Plan. Up to 2.5 million cubic yards of material will be placed along 19,200 linear feet of beach (1.7M in Wild Dunes and 800K on the southern end of the Island.) 

The nourishment will be separated into three separate reaches and involves construction of a dune and a berm.

The material will be dredged from an offshore borrow site located around ~2 miles southeast of the Island Pier.

Alternatives Analysis

The Isle of Palms City Council has voted to hire Foth/Olsen to conduct a study of the City’s beach restoration strategy.

Bringing in a new contractor could introduce fresh and innovative approaches aimed at extending the longevity of future sand placements, reducing the frequency of large scale restorations.

Any recommended alternatives would need to be implemented within a few years of the 2026 restoration project to help maximize the lifespan of the newly placed sand.

Where will construction occur?

View this map in full screen ➜

Tentative Construction Schedule
Pre-Construction Meeting30 June
Contractor mobilizationJuly
Anticipated first day pumping in Reach 127 July
Reach 1 nourishment duration50 days
Anticipated first day pumping in Reach 218 September
Reach 2 nourishment duration45 days
Anticipated first day pumping in Reach 310 Nov
Reach 3 nourishment duration45 days
DemobilizationDecember

 

Frequently Asked Questions (FAQs)

Will the beach be closed?

No. Beach renourishment work will take place in sections of approximately 300 yards at a time.

In most cases, pedestrians will be able to walk around the fenced work area. The only exception may be during temporary dune construction activities, when access around a work zone could be briefly restricted.

Beachgoers will also be able to safely cross the dredge pipeline using sand ramps to access the ocean.

Will the project be loud or disturbing at night?

This project will require heavy machinery operating around the clock. Residents may notice some light and backup alert sounds during nighttime hours. Work is expected to progress at a rate of 100–300 feet per day, so any disturbances in your area should pass within a night or two.

 

What will construction look like?

 

How is this project funded?

The City has received $1.5 million of the total $5.3 million requested in state funding for the major beach renourishment project. An estimated $27 million will come from local sources, including funds raised by the Wild Dunes Community Association, to complete the work. The amounts of each contribution are still to be determined.

All other City beach restoration efforts are being funded through a combination of the City's Beach Preservation Fund, Wild Dunes Community Association (WDCA) contributions, and state and federal sources.

Why is the project starting during the summer season?

Beginning construction during the summer proved to be the most cost-effective approach. By moving forward during this timeframe, the City saved approximately $10 million compared to alternative construction schedules.

View Coastal Science and Engineering's presentation of June 2026 to City Council ➜

Updates

August 10, 2026 – Work in front of Mariner's Walk and Shipwatch is now complete and the beach area is fully open to the public. The fenced construction area has progressed north, spanning from Summerhouse to Port O' Call.
August 5, 2026 – After the crew assessed the weather conditions yesterday morning, the dredge prepared for tow from the Charleston harbor out to the Isle of Palms borrow area. The dredge began pumping sand again around 3:00 pm (08/04).
August 4, 2026 – After assessing the conditions offshore, crews are planning to tow the dredge out to the Isle of Palms borrow area later this afternoon. Dredge Wadmalaw has been down in the Charleston Harbor for the past few days due to weather offshore.
August 3, 2026 – Dredge Wadmalaw is in the staging area near Fort Johnson in the Charleston Harbor due to inclement weather offshore. Crews are continuing to monitor the weather and anticipate towing back out to the borrow tomorrow (08/04) afternoon if weather allows.
August 1, 2026 – Dependent on weather, beach restoration operations may have a delay over the next 24 to 72 hours as a storm passes. The dredge will likely pull in to the harbor this afternoon to wait out a storm that’s coming through Sunday (08/02). They will consolidate the worksite and continue dredging as soon as possible.
July 30, 2026 – Beach crews installed a section of HDPE pipeline and the y-valve, allowing us to minimize our footprint on the beach. The rear fence has now moved up to station 288+00 (Beach Club Villas). They are currently pumping sand around station 291+00 (at the property line between Mariner's Walk and Shipwatch). The work area currently spans most of Mariners Walk and they are Moving north...
July 27, 2026 – Crews installed the floating pipeline on Monday morning (July 27), after which dredging operations began later that day. The dredge Wadmalaw was positioned in Shipyard Creek on Saturday evening (July 25) as crews continued final preparations for the Isle of Palms beach renourishment project. Offshore, crews successfully installed an additional 2,000 feet of submerged pipeline. On...
July 23, 2026 – Marinex has now installed approximately 9,000 feet of pipeline, with about 2,000 feet remaining before dredging operations and sand placement on the beach can begin. Installation has been delayed by rough offshore weather, which has prevented crews from completing the final section of pipeline. Current forecasts indicate a favorable weather window this weekend, allowing the...
July 20, 2026 – The beach renourishment project has experienced a slight delay due to weather. Marinex has successfully installed approximately 9,000 feet of the 11,000-foot pipeline needed to transport sand from the dredge to the beach. However, high winds prevented crews from completing the remaining section. The dredge is fully mobilized and ready to begin operations as soon as the final...
Staging on beach
July 9, 2026 – You may have already noticed construction equipment staged on the beach near Mariner's Walk. This marks the beginning of the 2026 Beach Renourishment Project. The contractor barged the heavy equipment in via Dewees Inlet, minimizing the impact on traffic and the City's road network. Onshore and offshore benthic samples required as part of the permit special conditions was conducted...
6 July,2026 – Mobilization is expected to begin tomorrow. Equipment will be transported by barge to the Isle of Palms via Dewees Inlet. Residents may notice equipment and crews on the beach, but no significant beach closures are anticipated. The dredge is expected to arrive in approximately 10–14 days. More updates will follow.
June 26, 2026 – Coastal Science and Engineering (CSE) has provided us with the latest estimates on a construction schedule available on our beach page. Will the beach be closed? No. Beach renourishment work will take place in sections of approximately 300 yards at a time. In most cases, pedestrians will be able to walk around the fenced work area. The only exception may be during temporary dune...