Waterway Blvd Multi-Use Path Elevation Project

Funding Source:

$5.8M construction (phase 1&1A on golf course- $1.4M; 

phase 2 on Waterway $2.9M; 

phase 3 on private property $1.5M) + $512k engineering. 

City awarded $980K Grant from FEMA Hazard Mitigation Grant+$1.25M state budget allocation for construction.

Updates

Update - September 2024

Monday, October 07, 2024
  • Staff met with FEMA and executed the grant agreement. FEMA advised on necessary next steps to change the scope of the project to increase the level of $1.1M ( $157K Design & Permitting - Capital Projects Fund. City seeking $990K Grant from FEMA Hazard Mitigation Grant for construction) Waterway Boulevard Multi-Use Path Elevation Project protection from 6’ to 7’, which is being worked on now with the City’s grant consultant.
  • Staff, engineer , Wild Dunes staff, and Wild Dunes golf course contractor met on site to discuss the incorporating flood mitigations modifications into the planned golf course improvements. The golf course contractor is working on providing a cost estimate to incorporate the flood mitigation into the project.

Update - August 2024

Monday, August 12, 2024

T&H anticipates finalizing the design and initiate the permitting process in September. FEMA announced award of approx. 1M grant for project.