Update on 2026 Offshore Beach Renourishment Project

6 July,2026 – Mobilization is expected to begin tomorrow. Equipment will be transported by barge to the Isle of Palms via Dewees Inlet. Residents may notice equipment and crews on the beach, but no significant beach closures are anticipated.

The dredge is expected to arrive in approximately 10–14 days. More updates will follow.