June 26, 2026 – Coastal Science and Engineering (CSE) has provided us with the latest estimates on a construction schedule available on our beach page.
Will the beach be closed?
No. Beach renourishment work will take place in sections of approximately 300 yards at a time.
In most cases, pedestrians will be able to walk around the fenced work area. The only exception may be during temporary dune construction activities, when access around a work zone could be briefly restricted.
Beachgoers will also be able to safely cross the dredge pipeline using sand ramps to access the ocean.
Will the project be loud or disturbing at night?
This project will require heavy machinery operating around the clock. Residents may notice some light and backup alert sounds during nighttime hours. Work is expected to progress at a rate of 100–300 feet per day, so any disturbances in your area should pass within a night or two.