October 5, 2026 – The dredge is being moved to Charleston Harbor due to rough offshore conditions forecast over the next several days.
Before suspending dredging operations, beach crews completed renourishment through the Seagrove Villas area, bringing Reach 2 to nearly 90% completion.
Marinex will continue monitoring offshore conditions and will resume dredging as soon as weather allows.
Based on the contractor’s latest schedule, Reach 2 is still anticipated to be completed by the end of the week.