August 25, 2026 – The dredge is currently down and stationed in the offshore borrow area as crews are towing additional subline offshore to be installed later today. The dredge will resume production once the additional subline is installed.
Beach crews are currently working just north of Ocean Club and have a fenced construction zone starting from Seascape.
Yesterday (08/24) the dredge removed an estimated 38,000 cubic yards of material at a rate of about 2,400 Cyds/Hr, advancing the widened beach roughly 50 feet from the day prior.